Project Description
Executive design and execution of the works for the expansion of the San Paolo in Agro Reservoir in Salice Salentino – 2nd section of the Sinni Aqueduct
The executive design and execution of the second section of the aqueduct consisted in the doubling of the Jonico Branch of the Lecce Aqueduct Siphon with a 1.4 m diameter steel pipeline from the new San Paolo reservoir to the existing Seclì reservoir for a total length of 37.3 km.
Location: Lecce
Function: Hydraulic-aqueduct works
Client: Acquedotto Pugliese S.p.A.
Contract value: 13,0 milion euros
Completion: 2012
Highlights: Pipeline of 1.4 m diameter approx. 37 km long m; water catchment works, aqueducts, supply and laying of pipelines